Progress report on the Seaport's Whaleboat(s)

A shapely lass

A work in progress, to be sure, and progress is being made.

Maststep,

rudder and

loggerhead. 
The loggerhead is a kind of bollard around which the harpoon line is turned to ease the strain.

The massive bow chocks seen in this photo were designed to take the strain of the harpoon line once a whale was in play.

all photos copyright Thomas Armstrong
 
 
 
The Seaport's whaleboat is coming along. Most of what remains are the bits and pieces that will pull it all together, and the parts, some already in place, exclusive to a whaleboat. The main task ahead is building and fitting the spars and sails.
ISM,via the boatshop, is looking to build a second whaleboat for the Morgan, and possibly the spars for all the project boats. The list is growing. There's the Rocking the Boat build, Lowell's has started theirs, Beetle Mfg. Co. is building and word has it that The Apprenticeshop and Alexandria Seaport have or will soon begin building. I'll hopefully have updates on all these projects soon.
The latest info I have is that the second whaleboat and the rig building projects at Workshop on the Water are still only partially funded.  If you are interested in helping, please contact Lily Williams in the development office at ISM. 
 
originally posted on Whaleboats for the CW Morgan by Thomas Armstrong



Wednesday, July 4, 2012

A smattering of the whaleboats around Mystic Seaport








all photos copyright Thomas Armstrong


At Mystic Seaport over the weekend for the WoodenBoat Show, I kept running into whaleboats. While these shots are of three different boats, there is a fourth, in the water, which I thought I had captured as well, but apparently not. Guess I'll need to go back. None of the  Morgan's original boats survive, though these replicas do apppear to have some age.

Be sure and look to 70.8% for a piece on the planking of the Morgan, an astounding undertaking. 
 
Geoff McKonley was at the show and promises to update me on Rocking the Boat's progress. I also met with Graham McKay of Lowell's Boat Shop in Amesbury MA. who reports he's 70% funded and is looking to start building in October, feeding us updates regularly. I also heard that the Apprenticeshop will be building a whaleboat as well, though I have yet to confirm this.

originally posted on Whaleboats for the CW Morgan by Thomas Armstrong

Thursday, June 28, 2012

Whaleboat Update

 

 Newt Kirkland helping John Schwarzenbach installing ribs. Tough job! Very meticulous.

All the ribs installed

John and Newt checking position before installing the port
riser, which is the upper, inner plank.
 

 Newt and John actually positioning the centerboard
for install. Not as simple as it looks!

Newt sitting on the installed centerboard, working at getting
the long bolts in. They go all the way through the centerboard and the
keel! There were issues, but Newt got it done.

The floor of the warp box, before the thigh board
installation.
 

Thigh board being installed in the bow. The half circle is called the clumsy cleat. Used by for the (harpooner?) to  lean or brace against.

The hinged mast tabernacle, useful for quickly lowering sail during a whale hunt.

All photos and captions above courtesy George Clarke 

 Bow shot as of June 6

Gina Pickton filling me in on the progress made.

This stern shot clearly shows the combination of carvel and lapstrake planking.


It's my understanding that the combination of two different styles of planking styles is practically motivated. Carvel, in the water, is much quieter than lapstrake, with lapstrake being stronger above to handle increased stresses.

Centerboard thwart

Looking toward the bow from just behind the centerboard case. That spar does not belong to the whaleboat.
The above six photos and captions copyright Thomas Armstrong

First let me welcome a new eye and voice helping out with this post. George Clarke is a workshop volunteer and has been photographing the whaleboat progress and posting to the WOW Facebook  page. I welcome his help.

It's been quite some time since we posted here and a lot has been done. I asked Gina for a laundry list of work accomplished since our last post:

"Here’s a list of all that has been done in the past few months. We’ve made some good progress. The whaleboat was not worked on during the month of March as the whole crew moved over to make cannon carriages or the month of June when the whole crew went to work on Whitehalls.  

All the frames
Centerboard and Centerboard trunk
Lions tongue
Seat riser and thwarts
2 Ceiling planks
Sheets
Bow chock
Oarlocks
Mast trough
Mast Tabernacle
Loggerhead
Rudder
Warp Box
Aft deck
Quarterchocks"

I recently received an email from Lowell's Boat Shop vis a vis their beginning a fund raising campaign for their whaleboat build. If you are in their area, please give them a hand.

Also must see is Tom Jackson's piece on the whaleboats in the currents section of WoodenBoat #226, May /June 2012. 

Hopefully we'll have an update from Geoff McKinley at Rocking the Boat soon. In the meantime you can enjoy a flickr set of their progress here. (scroll down a bit)

Originally published by Thomas Armstrong in Whaleboats for the CW Morgan


Monday, January 9, 2012

Planking completed

It’s been a busy couple of months and the planking is now complete.



Volunteer Rachel Gordon, back for Christmas break, is helping with the frame patterns.



All the work last year bending frames has come in handy as framing has been started. Installing each frame is a lot of work and it comes in handy having a supply of frames already made.




First mold is no longer needed and was removed to make more room.



Randy Dearlove checking his measurements.



Photos and captions courtesy Gina Pickton



Lowell's Boat Shop

All rights reserved



Looks like the good folks at the boatshop have indeed been busy. Planking is finished and framing begun. Notice in the first photo that the top two planks are lapstrake. I'm sure you'll all join me in extending Gina, Bruce, Jeff Huffenberger, Newt Kirkland and all the volunteers involved a hearty well done. There's lots yet to be done but it's nice to see the project advancing and looking like a whaleboat. I'll get down there soon and follow up with some more photos.

Interestingly, I received an email from Graham MacKay, Manager of Lowell's Boat Shop in Amesbury MA saying that they are currently fundraising to build yet another whaleboat for the Morgan, beginning this coming fall. Lowell's was for decades a successful family owned concern, is on the National Historic Register and is somewhat uniqe in being both an ongoing commercial boatyard and a museum. From the website:

Established in 1793, Lowell's Boat Shop is the oldest continuously operating boat shop in the United States and is cited as the birthplace of the legendary fishing dory. Lowell’s is the only remaining survivor of the area’s world-renowned dory manufacturing industry that produced in excess of a quarter of a million dories over a period of two centuries. Building more than 2000 boats in 1911, this business was one of the first in the Nation to employ a seminal form of assembly line manufacturing.
With the founding of his company, Simeon Lowell made radical innovations to traditional boat design. Known for their efficiency, durability and sea worthiness, Lowell dories became the heart and soul of the Gloucester fishing fleet. In the waning days of the great fishing industry, recreational boaters turned to Lowell dories for the same qualities that attracted the fishermen. Rowing clubs, hunting camps, the Boy and Girl Scouts and the Lifesaving Service all sought Lowell dories and skiffs for their maritime experiences.
Conveyed through seven generations of the Lowell family, Lowell’s Boat Shop was passed to the Odell family in the 1980’s and then to the Newburyport Maritime Society in the 1990’s. In 2006, Lowell’s was purchased by Lowell’s Maritime Foundation, an independent non-profit group with the mission of leading this National Landmark and Working Museum through its third century of wooden boat building.


I'm sure to be hearing more from Graham in the coming months and hope to keep you informed about this project as it progresses. Lowell's makes, among others, this finely kitted out sailing dory.

Original post Thomas Armstrong for Whaleboats for the CW Morgan

Sunday, November 13, 2011

Planking taking shape


Wendy Byar


Four planks up counting the garboard




Plank 5 going on





5th plank
The 2nd thru 6th planks are clench nailed to battens. It is sort of like carvel with a backing plank. I suppose the battens reinforce the seams since the planks are thin for lightness and they are not nailed to the molds. It takes some care with the anvil and hammer to keep everything aligned so neither the planks or battens split. The frames are fitted after the boat is planked. It is taking a beautiful shape. The 5th and 6th planks were wumped, or prebent to a cupped shape before being hung. the last two planks will be hung lapped.

Courtesy Wendy Byar


Gina Pickton

Wendy Byar and Newt Kirkland attaching a plank



Knot drilled out with Forstner bit and replaced with a bung




Jeff and Newt have been making good progress with planking the boat. The process of putting a plank on is the same for each one, a set of steps that gets repeated over and over again until all 16 are on

We start by spiling the pattern and preparing the boards. The cedar we have is not long enough to span the entire length of the 28ft whaleboat so we have to scarf two pieces together. After planing each board to the proper thickness, we use our pattern to cut the proper shape into the boards, making sure to leave enough room for the scarf. Next we repair any parts of the plank that need it, drilling out knots and replacing them with bungs and adding dutchmen where necessary.









As the planks work their way up around the turn of the bilge, they get wider and wider. In order for the board to take the curve we bend them before attaching them to the boat. To do this we use a process called Whomping.

You can see more about how we do this by watching the videos above. Narrated by John Schwarzenbach

courtesy Gina Picton


Thomas Armstrong

Wen Byar clench nailing

From Wendy's blog Green Boats:
"Here is the skinny. We drill the holes through the plank and batten, and place the nail oval perpendicular to the grain. Back it with the iron next to the hole and tap the nail thru from the plank side until it just clears the batten. Move the iron over the nail. Hold it at an angle so the nail starts to turn back into the batten. Tap it home flush with the plank surface."


I was at the workshop Thursday and it was a dark day, which produced this combination of natural and artificial lighting.


She's a long boat at 28'


A nicely turned bilge


Newt and Jeff


She's really taking shape

photos Thomas Armstrong


I made my way down to the Workshop last Thursday to see the progress on the whaleboat. Coincidentally Gina Pickton and the new workshop director Bruce MacKenzie (more on Bruce later @ 70.8%) had put together some photos and videos for me. Wen Byar had also sent me some updates. The boat looks swell and is really graceful, and the work looks top notch. My first impression was of how long, and how sweet she is. The videos will outline the process of wumping or whomping, basically steaming a plank to make it more pliable form fitting the curve of the boat. Thanks ladies and gents, you are doing exceptional work. Special thanks to John Schwarzenbach for his narration on the videos.


Original post Thomas Armstrong for Whaleboats for the CW Morgan

Tuesday, September 20, 2011

Planking begins...


Garboard in place and a new plank being fitted.



Same



Frames!



More frames on the bending jig



This shot shows how the garboard fits into it's rabbet, or groove, on the keel.



This from about eye level



This photo shows how the garboard conforms to the molds.


all photos Thomas Armstrong



After a great afternoon aboard Gazela for the pirate battle (see 70.8%), I dropped in on Gina at the boatshop to see what progress had been made of the boat. They've started planking but only just. Much more time has been spent over the last month or so bending the approximately100 frames needed for the boat. The actual figure is around 76, but Gina explained they wanted a few extras so they would not have to do them later. As you can see there's a rather impressive pile!
As for the planking, both garboards have been fitted into their rabbet along the keel and a partial first plank or strake as well. Once the frames are all done the planking should proceed quickly. Exciting!